Portsmouth UV CIPP Lining Project Dashboard
Last Updated
Loading...
π§ Natural Language Command
Ask something like: "How many tasks are not started?" or "What is the slowest job?"
π Time-Aware Narrative Report
π Additional Project Information
This information will be included in project reports and documentation
0 / 300 charactersData Backup & Restore
Use Export/Import to save your work before refreshing the page
π€ AI Predictive Insights
Advanced analytics powered by machine learning
Project Completion Forecast
Current pace suggests early completion. Consider reallocating resources to other projects.
Performance Optimization
M275 tasks show clustering opportunity. Batch processing could save 15% time.
Risk Assessment
15% chance of rain delays next Tuesday. Consider rescheduling outdoor tasks.
Smart Recommendations
Route Optimization
Group Baffins Rd tasks (GY-773, GY-11670, GY-11664) to save 45 minutes travel time
Resource Reallocation
Current pace allows for crew to assist other projects after Aug 20th
Quality Assurance
Schedule QA inspections for completed Goldsmith Ave sections before final sign-off
Performance Metrics Input
Planned vs Actual Time
Performance Metrics
Daily Progress vs Planned
Resource Analysis
Project Tasks - Portsmouth UV CIPP (Aug 5-22, 2025)
| Date | GY ID | Location | Length (m) | Actual Length (m) | Planned (hrs) | Actual (hrs) | Status |
|---|